Case: AT-2000 Raise Boring Machine in Guinea — Mamu Tunnel

Project Case Study: AT-2000 Raise Boring Machine Successfully Completes Ventilation Shaft in Guinea

Project Location
Mamu Tunnel Project, Guinea, West Africa
Project Type: Tunnel Ventilation Shaft Construction

Equipment Model
AT-2000 Raise Boring Machine
Developed by Hunan Yier Mining Technology

Technical Parameters

Shaft: 3# Ventilation Shaft

Drilling Operations: Pilot-Hole Drilling and Reaming

Geological Conditions: Hard and unstable rock formations with multiple fractured zones

Key Geological Challenge: Fractured rock zone encountered at a depth of 53 m

Project Challenges

Complex geological conditions involving hard rock, unstable formations and fractured zones

Potential risks of ground collapse and water inflow

Reduced reaming efficiency and larger rock fragments in fractured formations

Language barriers between Chinese engineers and local Guinean personnel

Limited material supplies and unreliable network connectivity at the project site

Solution and Results

Adaptive Drilling Control: Yier Mining's on-site service engineer adjusted drilling speed and feed pressure and applied low-pressure pullback to help the machine pass through the fractured rock zone at 53 m depth.

Continuous Condition Monitoring: Discharged rock fragments were monitored throughout reaming to support timely adjustments to operating parameters.

Full-Process Technical Support: On-site assistance covered machine positioning, rig setup, pilot-hole drilling, reaming-head installation, reaming, machine recovery and reaming-head removal.

Local Operator Training: Guinean technicians received practical training in equipment operation and construction procedures, helping develop the skills needed for future independent operations.

Successful Shaft Breakthrough: The AT-2000 Raise Boring Machine successfully completed the 3# ventilation shaft, overcoming challenging geological conditions and on-site operational difficulties.

Customer Feedback
The project demonstrated effective cooperation between the Chinese and Guinean project teams. The supplied project report highlights the value of Yier Mining's on-site technical assistance and practical training.

Key Takeaway
The Mamu Tunnel Project demonstrates the AT-2000 Raise Boring Machine's application in challenging geological conditions, supported by adaptive drilling control, on-site engineering expertise and hands-on training for local technicians.

Related Products


YIER TECHNOLOGY

Contact Us

What's app: +86-186 7483 6863 Mia Su

What's app: +86-198 9624 1275 Betty Zhou

Company address: No.320 Changqing Road,Kaifu District,Changsha City,Hunan Province,China YIER Science and Technology Industrial Park

Submit
No data

No data

business license

Powered by www.300.cn ChangSha