Case: ATM-1000L Slot Raise Boring Machine in Nei Menggu— Yubang Mine
Hotline:
Project Case Study: ATM-1000L Slot Raise Boring Machine at Yubang Mining
Project Location
Country: China
Mine: Yubang Mining, Chifeng, Nei Menggu
Project Type: Inclined Blind Slot Raise Construction
Equipment Model
ATM-1000L Slot Raise Boring Machine
Technical Parameters
Number of Raises: 2
Drilling Depth: 20 m and 16 m
Inclination: 70°
Construction Efficiency: 30–40 min/m
Rock Conditions: Loose rock and unstable roof
Project Challenges
Precision in Inclined Blind Raise Construction
The 70° inclination required accurate machine positioning and reliable drilling alignment to achieve successful breakthrough.
Unstable Roof and Ground Conditions
Loose rock and roof scaling hazards increased operational risks. Existing rock bolts, concealed beneath shotcrete, also required careful monitoring to avoid damage during drilling.
Pressure Stability During Operation
The inclined setup created challenging loading conditions, with potential pressure fluctuations and upward or downward support pressure loss. Stable equipment operation required continuous monitoring and timely adjustments.
Solutions and Results
Flexible Machine Positioning
The ATM-1000L features longitudinal forward tilting of 80°–90°, backward tilting of 60°–90°, and lateral swing of ±30°, enabling adjustment to different drilling orientations, including the project's 70° inclination.
On-Site Technical Support
Yier Technology service engineer Guo Yi provided on-site support throughout construction. By combining manual and automatic pressure compensation, monitoring pressure gauge readings, and adjusting equipment parameters according to site conditions, the team helped maintain stable operation.
Efficient and Mechanized Construction
The machine completed two inclined blind raises, measuring 20 m and 16 m in depth, at a reported construction rate of 30–40 minutes per meter. The project also reported a shift output of 9 m over eight hours.
The mechanized drilling process and wireless remote control allowed operators to control the equipment from a safer position. The team monitored the drill bit and discharged cuttings for signs of metal debris or possible rock bolt damage, stopping work for inspection and corrective action when abnormalities were identified.
The equipment does not require a conventional concrete foundation, helping simplify site preparation and reduce preliminary construction work.
Project Results
The ATM-1000L successfully completed both 70° inclined blind raises, achieving breakthrough with a reported construction rate of 30–40 minutes per meter. The project demonstrated the machine's ability to handle inclined raise construction while combining efficient drilling, responsive technical support, and risk-control measures.