Case: AT-4000L Raise Boring Machine in Fujian — Zijinshan Copper Mine
Hotline:
Project Case Study: AT-4000L Raise Boring Machine Achieves 1,069 m of Raise Construction at Zijinshan Copper Mine, China
Project Overview
Project Location: Fujian, China — Zijinshan Copper Mine
Equipment Model: Yier Technology AT-4000L Raise Boring Machine
Delivery Date: March 2025
Cumulative Raise Construction: 1,069 m
Raise Diameter: 4 m
Maximum Reported Raise Depth: 120 m
Drilling Efficiency: Approximately 1 m/h for pilot drilling and reaming
Minimum Reported Deviation Rate: 0.1%
Project Challenges
Single-Pass Construction of a 4 m Diameter Raise
The project required a 4 m diameter raise to be completed in a single pass. This posed significant challenges for drill string stability and cuttings removal, as even minor deviations could cause drill string jamming and affect construction progress and quality.
Reaming Head Recovery at the Raise Collar
After raise construction, the 15-ton reaming head had to be recovered from the raise. However, conventional equipment was not suitable for the challenging site conditions, making this operation particularly difficult.
Precision Breakthrough into an Existing Station Opening
One raise had to accurately connect with a previously constructed station opening, with a maximum allowable deviation of 300 mm. Excessive deviation could damage the existing structure and pose serious safety risks.
Solutions and Results
Optimized Drilling Parameters for Large-Diameter Raises
Yier Technology's technical team worked closely with the mine team to optimize drilling parameters according to changing rock conditions. Through repeated on-site testing, they developed a targeted approach combining low rotational speed in hard-rock sections with high flushing flow for efficient cuttings removal. Meanwhile, the operators kept drill string deviation within 0.3%, helping ensure accurate raise formation.
On-Site Guidance for Reaming Head Recovery
Yier Technology's service engineer, Deng Guangping, provided on-site guidance throughout the reaming head recovery process. From load calculations for the welded gantry to precise control of the lifting angle, he guided the team through every critical step, ensuring the safe and successful recovery of the 15-ton reaming head.
Precision Alignment with an Existing Station Opening
To ensure accurate breakthrough, the project team strengthened alignment checks and improved drill string angular control from 1° to within 0.5°. The team repeatedly verified the station opening's position, marked reference points at the raise collar, and established alignment lines. Drilling speed was also adjusted in response to changing rock conditions, enabling the raise to connect accurately with the existing opening.
Project Results
1,069 m of cumulative raise construction completed.
Five ventilation raises, each 4 m in diameter and 120 m deep, completed.
Precision Breakthrough: A 125 m raise was accurately connected to an existing station opening, with an actual deviation of only 150 mm, well within the allowable limit. The completed raise had a smooth surface and met the mine's quality requirements.
Successful recovery of a 15-ton reaming head with on-site technical guidance.
Customer Recognition
Yier Technology's technical support and collaboration with the Wuping Zijin project team helped resolve several construction challenges. In recognition of the team's service, the mine presented Yier Technology with a commemorative banner.