Project Case Study: AT-2000TB Raise Boring Machine Successfully Completes a 100 m Inclined Raise at Chongli Zijin Mine
Project Location
Country: China
Mine: Chongli Zijin Mine
Project Type: Underground Mining – Inclined Raise Construction
Equipment Model
Equipment Model: Yier Technology AT-2000TB Raise Boring Machine
Design: Compact, modular raise boring machine developed for inclined raises in small and medium-sized mines
Transportation: Self-propelled wheeled movement and rail towing
Technical Parameters
Completed Raise Depth: 100 m
Inclination: 30°
Measured Deviation: 0.97 m
Deviation Rate: 0.97%
Total Construction Period: 44 days
Rock Conditions: Potassic alteration rock and silica-potassic altered rock
Other Project Raises: 48.85 m at 60° and 67 m at 42°
Project Challenge
Stable Machine Setup: The 30° inclination required a secure foundation and precise machine positioning to prevent movement during drilling.
Strict Alignment Requirements: Accurate control of the drilling angle and trajectory was essential for successful breakthrough.
Difficult Slag Removal: Rock fragments accumulated at the bottom of the raise during reaming, causing repeated crushing, drill jamming, and reduced advance rates.
Hard Rock Conditions: Increased thrust pressure in hard rock could shift the support frame and affect drilling efficiency.
Solution and Results
Customized Setup for 30° Inclined Drilling
The team prepared a level, hardened concrete foundation and installed a customized 60° support frame to establish the required 30° drilling angle. Laser alignment and anchor-bolt reinforcement helped improve positioning accuracy and operational stability.
Optimized Reaming and Slag Removal
The reaming cutter was specially designed with optimized connecting rods, stabilizing blocks, and scraping plates. After testing different methods, the team introduced direct water flushing to remove accumulated rock fragments, reduce repeated crushing, and restore normal reaming operations.
Successful Breakthrough in 44 Days
The AT-2000TB successfully completed the 100 m deep raise at a 30° inclination, achieving a measured deviation of 0.97 m and a deviation rate of 0.97%.
The overall construction took 44 days:
Machine setup: 3 days
Pilot hole drilling: 10 days, averaging 9 m/day
Reaming cutter installation: 1 day
Reaming: 30 days, averaging 3 m/day
The successful breakthrough demonstrated the machine's adaptability to shallow-angle raise construction and the team's ability to overcome challenging slag removal and positioning issues.
Customer Feedback
The successful completion of the 100 m inclined raise provided essential access and ventilation support for subsequent ore block extraction, demonstrating the practical value of the AT-2000TB in underground mining operations.