Case: AT-2000L Raise Boring Machine in Fiji — Vatukoula Gold Mine
Hotline:
Project Case Study: AT-2000L Raise Boring Machine Completes a 150 m Ventilation Shaft at Vatukoula Gold Mine, Fiji
Project L ocation
Country: Fiji, Oceania
Mine: Vatukoula Gold Mine
Project Type: Underground Ventilation Shaft Construction
Vatukoula Gold Mine is a long-established operating gold mine in Fiji. This project involved the construction of an underground ventilation shaft to support the mine's ventilation requirements.
Equipment Model
AT-2000L Raise Boring Machine
Manufacturer: Hunan Yier Mining Technology Co., Ltd.
Technical Parameters
Borehole Diameter: 2,000 mm
Drilling Depth: 150 m
Inclination: 88°
Application: Underground ventilation shaft construction
Final Result: Successful shaft breakthrough and acceptance by the mine
Project Challenges
The project required the construction of a large-diameter, deep ventilation shaft under underground mining conditions. Key challenges included:
Underground Equipment Installation: Moving and installing the raise boring machine in the mine's underground workings.
Operational Safety: Establishing appropriate safety protection and ensuring proper equipment preparation before and during construction.
Logistics and Site Coordination: Coordinating drill rod transportation, equipment installation, and emergency water supply arrangements underground.
Technical Support and Training: Providing on-site operator training and continuous technical assistance throughout the construction period.
Solution and Results
Hunan Yier Mining Technology provided the AT-2000L Raise Boring Machine together with comprehensive on-site technical support from February to May.
The after-sales engineer, Yixunfei, first delivered systematic safety training and practical equipment instruction to the mine's personnel. The team then completed ground-level equipment commissioning and inspections before the machine was moved underground.
During installation and construction preparation, the service team coordinated underground equipment positioning, safety protection, drill rod transportation, and an emergency water supply system. On-site technical support continued throughout the project to help ensure smooth operations.
Project Results:
Successfully completed a 2.0 m diameter, 150 m deep ventilation shaft at an inclination of 88°.
Achieved successful shaft breakthrough.
Delivered a smooth, regular shaft wall that met the mine's construction requirements.
Passed on-site inspection and received positive feedback from the mine's team.
Provided practical equipment operation and safety training to support the customer's on-site capabilities.
Customer Feedback
During the on-site acceptance process, the mine's team confirmed that the shaft wall was smooth and that the completed shaft met the required construction quality standards.
The customer also positively evaluated the equipment's performance and the service team's cooperation and technical support.